Beverly Fink Residence
BEVERLY FINK RESIDENCE, VA
PC#2001-2135N
Description of Role: Primary Environmental Consultant/Contractor
Key Personnel: Andrew Alden, Christopher M. Swan, III, Chris Lalli, Carl
Cirillo
Project Cost: $56,323.70 to date
Time Period of Project Work: April 2001 to Present
Client: Ms. Beverly Fink
Client Representative: Ms. Beverly Fink
Regulatory Agency: Department of Environmental Quality
Regional Office(s): West-Central Regional Office
Introduction:
The Beverly Fink Residence is a private residence located at 5701 Cove
Road, in Roanoke County, Virginia. The site is owned by Ms. Beverly
Fink.. Environmental Engineering, Inc. (EEI) is presenting this project
as an example of EEI’s ability to provide initial abatement measures and
site characterization at a residence impacted by a small heating oil
tank petroleum release site, which is located in a neighborhood with
nearby domestic wells and documented surface water impact via the local
storm sewer system.
This example also demonstrates emergency response capabilities in terms
of providing services to abate hazardous conditions impacting receptors
in proximity to the release site. All professional/field services and
equipment discussed in this example were solely provided by EEI, unless
explicitly noted in the Scope-of-Work or Staff Resources and Involvement
sections of this project overview.
Scope of Work:
This petroleum release was discovered in March of 2001 when a subsurface
oil line between a small heating oil AST and the associated furnace,
located in the residence basement, was found to be leaking. Near the
time of the petroleum release, No. 2 fuel oil was found to be entering
the stormwater sewer located in front of the house. Heating oil was
traveling to the stormwater sewer outfall and impacting an unnamed
tributary of Peter’s Creek. The DEQ had initially contracted with an
emergency response contractor to establish and maintain
petroleum-absorbent booms at the storm sewer outfall.
Once EEI was contracted by the homeowner, responsibility for maintenance
of the booms at the stormwater sewer outfall transitioned smoothly from
the DEQ to EEI. EEI continued to monitor and maintain the booms on a
periodic basis. Booms were maintained by EEI for over one year, during
which time they were replaced as necessary. Great effort was made on the
part of EEI to schedule boom maintenance site visits to closely follow
significant rain events, which had previously caused free product to
migrate from the site to the stormwater sewer system.
EEI installed a monitoring/recovery well through the concrete foundation
floor of the residence basement. The water table below the Fink
Residence is very shallow, and was observed to be approximately 0.5 feet
below the top of the concrete basement floor at the time recovery well
was installed in April of 2001. Free product accumulated in this well at
a thickness of 0.03 feet. When the subsurface portion of the heating oil
supply line leaked, heating oil appears to have accumulated under the
Fink Residence basement floor.
In order to aggressively recover the released heating oil, a mobile DPE
and treatment system was operated at the site from April 12 through
April 19 of 2001. The DPE system was operated for an average of eight
hours per day, for six days, or a total of 48 hours. A 50-Kw mobile
generator powered the DPE system. The DPE event utilized the monitoring/
recovery well located in the Fink Residence basement for the recovery of
free product and petroleum-contaminated water.
A total of approximately two gallons (or 14 lbs.) of free product and
1,650 gallons of petroleum-contaminated water were recovered during the
48-hour DPE event. Based on TPH concentrations measured in air samples
collected from the air/water separator and the measurements of air
exhaust flow rate, the total mass of petroleum removed in the air stream
was estimated at 13.5 pounds. Based on the diesel-range TPH
concentrations of samples collected throughout the DPE event, the
over-all mass of petroleum removed in the DPE system effluent is
estimated at approximately 6.2 pounds as TPH. The total mass of
petroleum removed during the DPE event was approximately 34.0 lbs or
approximately 0.70 lbs/hr.
Ms. Fink reported that some water occasionally seeped through the
basement floor and into the basement following heavy rain events. It
appeared that when groundwater seeped into the basement, two mechanisms
caused subsurface petroleum contamination to quickly migrate away from
the Fink Residence. First, foundation drains located to the northwest
and northeast of the house apparently carried heating oil to the
stormwater intake located west of the house near Cove Road. Secondly, a
sump pump located in the basement periodically discharges petroleum
contaminated water to the home’s septic system located northwest of the
house. EEI assessed impact to the environment resulting from both of
these migration pathways.
EEI uncovered and checked the Fink Residence septic tank for the
presence of free product on April 11. Although petroleum sheen was
observed in the tank, no measurable free product was detected.
Three monitoring wells were installed on-site to assess the groundwater
quality along both of the identified petroleum migration routes. One
well was installed midway between the petroleum release source and the
on-site domestic well. These wells were installed using EEI’s hollow
stem auger drill rig using 4.25-inch I.D. augers.
Following well installation, the wells were sampled for petroleum
indicator compounds. Slug tests were performed on three of the four
monitoring wells in order to estimate hydraulic conductivity on-site.
EEI staff surveyed the monitoring well locations and elevations and
gauged all monitoring wells in order to calculate groundwater elevations
at each well. Groundwater elevation data, together with hydraulic
conductivity values, were used to determine interstitial groundwater
velocity on-site.
Dissolved concentrations of No. 2 heating oil constituents at monitoring
wells, MW-3 and MW-4 were found to be at, or slightly above, the
laboratory quantitation limit for all parameters tested. The horizontal
extent of dissolved-phase appears to be roughly delineated to the north
and west of the petroleum release source area. Free product and
dissolved-phase petroleum plumes are less defined to the south and east
of the Fink Residence. Laboratory analysis of a representative sample of
the on-site domestic well indicates that there is no current impact
there; however, trace concentrations of diesel-range petroleum
hydrocarbons were reported at the sentinel monitoring well, located
midway between the house and the domestic supply well.
At the conclusion of the IAM and the SCR, EEI recommended continued
monitoring of the site in order to track trends in free product
accumulation, petroleum migration, groundwater elevation, and
dissolved-phase petroleum concentrations. The DEQ directed the R.P. to
conduct Post-Site Characterization (PSC) monitoring on-site for a period
of one year. The PSC monitoring phase of corrective action included
continued maintenance of the booms, monthly well gauging, quarterly well
sampling, and the installation of a vapor extraction (VE) system in the
basement of the residence. EEI designed, fabricated, and installed a VE
system, which was connected to the monitoring/recovery well previously
installed in the Fink Residence basement.
The VE system operated for approximately three months with success,
however, it would often shut down due to water accumulation in the
system’s knockout tank. EEI made suggestions on alleviating this problem
with an automated pump out system for the knockout tank.
VE system modifications were never implemented because the results of
site monitoring indicated that risk levels on-site were acceptable as
based on the absence of free product for over one year, the results of
vapor monitoring in the residence basement, and results of quarterly
well sampling. The DEQ closed the pollution complaint in 2003.
Monitoring wells on-site were properly abandoned in January of 2004.
Other site closure activities are pending.
Staff and Resource Involvement:
Mr. Alden has provided engineering oversight and project management
assistance since 1999. Mr. Lalli has been responsible for scheduling of
personnel and field equipment to the project since 2001. Mr. Cirillo was
responsible for project management, which included all IAM activities,
drafting the IAMR. Mr. Rob Speiden was responsible for field management
of the monitoring well installations. Mr. David Tollefson was
responsible for design and fabrication of the VE system. EEI field
technicians collected all field data and provided support for the
operation of equipment and machinery. Equipment owned and operated by
EEI that was used on this project included a DeepRock™ hollow stem auger
drill rig, a mobile liquid ring pump DPE system, a 50Kw diesel
generator, and a 160 cfm SVE system.
|