Gas N' Shop Facility
VEENA CORPORATION – GAS N’
SHOP FACILITY, POLLUTION COMPLAINT NO. 98-1068
Description of Role: Primary Environmental Consultant/Contractor
Key Personnel: Christopher Lalli and Andrew Alden
Project Cost: $581,320 to date
Time Period of Project Work: 1998 to present
Client: Veena Corporation
Client Representative: Mr. Abdul Malik
Regulatory Agency: Virginia Department of Environmental Quality (DEQ)
Regional Office(s): West Central
Introduction:
Environmental Engineering, Inc. (EEI) is presenting this project as an
example of our experience in providing/performing environmental
consulting and contractual services under several of the release
investigation and corrective action phases that are defined under the
Virginia Petroleum Storage Tank Fund (VPSTF) program. This example also
demonstrates emergency response capabilities in terms of coordinating
and providing services to abate hazardous conditions impacting
receptors, both on, and immediately proximal to the release site. All
professional/field services and equipment discussed in this example were
solely provided by EEI, unless explicitly noted in the Scope-of-Work or
Staff Resources and Involvement sections of this project overview.
Scope-of-Work:
In December of 1997, the DEQ was notified of an apparent release related
to the USTs located at Gas N Shop in Roanoke, Virginia. Gasoline vapors
were detected on December 2, 1997 in the basement of the adjoining
property located at 1214 Hamilton Terrace. Emergency crews were summoned
and occupants were evacuated from the house until vapor levels
decreased. The operator of the subject facility, Mr. Abdul Malik,
commissioned tank tightness tests for each UST at the site. On December
7, 1997, all three existing USTs passed the portion of the tank
tightness testing procedure designed to indicate leakage at or below the
product level in the tanks. However, the ullage portion of the tank
tightness tests, designed to test tank tightness above the level of
product in the tanks, were not completed due to malfunctioning equipment
on the part of the testing contractor. The product distribution line for
one tank passed the test; however, tightness testing of the product
lines associated with the other two tanks could not be completed due to
apparent problems with the subject lines.
Veena Corporation, the owner, retained EEI’s services in May of 1998 to
perform release investigation activities at the referenced site. Site
check and initial abatement measure (IAM) activities were commenced by
EEI in May of 1998 and completed in August of the same year. The release
investigation included: 1) regulatory records review to investigate the
petroleum release history of the site; 2) residual-phase investigation,
that included the advancement of six soil borings on-site; 3) conversion
of three soil borings to groundwater monitoring wells for assessment of
separate- and dissolved-phase petroleum; 4) ambient air monitoring in
the basement of the impacted residence, and 5) limited risk assessment
activities. The results of this investigation determined that a
significant petroleum release was reported in 1991, and was addressed
under a previous pollution complaint (PC-91-1588). Elevated
concentrations of residual- and dissolved-phase petroleum were
documented in the northwestern portion of the site, in proximity to the
UST tank pit. Groundwater flow across the site was found to be tending
toward the west-northwest. Additionally, petroleum impacts in the
subsurface of the site were contributing to the formation of vapor-phase
petroleum, although detectable concentrations of vapor-phase petroleum
were not present at the time of sampling in the basement of the
residential dwelling. Identified potential receptors at risk from the
migration of vapor- and dissolved-phase petroleum included nearby
residences, an electric utility power station, and the Roanoke River.
Based on the results of this investigation, additional activities were
requested to further characterize the site.
The review of the Site Check/IAM report by the DEQ resulted in a request
for an addendum. Most of the activities conducted under the IAM phase
were repeated under this investigation; however, different activities to
note include: 1) performance of a soil vapor gas survey to evaluate
potential conduits for vapor-phase petroleum and; 2) vapor monitoring of
stormwater drop inlets and subsurface utility vaults. The results of
this investigation ascertained that the highest soil vapor
concentrations were on the western portion of the site, and there was no
direct correlation between utility corridors and vapor-phase petroleum
migration. Geologic, hydrologic, and dissolved-phase concentration data
suggested that two hydrostratigraphic units were present at the site.
Dissolved-and vapor-phase data indicated that residual-phase was likely
the primary source of subsurface vapor formation. Based on this
information, EEI recommended that soil vapor extraction be implemented
to remove residual- and vapor-phase petroleum.
Upon review of the IAM Addendum report, DEQ requested additional site
characterization activities to further determine the amount and extent
of petroleum hydrocarbons in the underlying groundwater, evaluate risk
to impacted and/or potential receptors, and to assess applicable
remedial technologies for site cleanup. The additional SCR activities
included: the installation of supplemental wells in the western portion
of the site; performance of waste load allocation calculations to
determine whether or not the Roanoke River was at risk from the
migration of dissolved-phase in the main component of groundwater flow,
and performance of a DPE pilot test. Elevated concentrations of
residual- and dissolved-phase were present in the newly installed wells,
and dissolved-phase appeared to be migrating off-site towards the
Roanoke River. Waste load calculations indicated that dissolved-phase
was not a threat to the Roanoke River. The week long pilot test was
successful at removing over 2000 lbs. of petroleum contamination from
the subsurface of the site and; 5) DPE application appeared to lead to
the migration and detection of separate-phase in one well on-site. Based
on the detection of separate-phase and previous vapor-phase impact to a
defined receptor, a Corrective Action Plan (CAP) was recommended to
develop remedial strategies to address all phases of petroleum impacted
in the subsurface of the site. A PSCR monitoring program was also
recommended to track and manually remove (absorbent socks and hand
bailing) separate-phase petroleum from the impacted well(s) on-site.
In February 2001, EEI completed a CAP that CAP identified the AEP Power
Station, nearby residences, and the Roanoke River to be at potential
risk from the off-site migration of separate, dissolved, residual, and
vapor-phase petroleum. Based on these potential risks, the CAP
recommended the implementation of DPE technology to simultaneously
address all phases of petroleum contamination; however, remedial
endpoints were not assigned for dissolved, residual, and vapor-phase
petroleum.
On the afternoon of April 2, 2001, residents at 1214 Hamilton Terrace
contacted the DEQ regarding the presence of gasoline vapors in the
basement and living quarters of their home. Subsequently, per DEQ
request, EEI responded to the emergency situation and conducted vapor
monitoring to assess the levels of gasoline vapors present at the
subject residence. Vapor concentrations were relatively low at all
measured points; however, EEI recommended the implementation of an
active ventilation system to encourage air turnover in the basement
structure. Upon receiving verbal approval from the DEQ, EEI installed
two ventilation blowers and associated exhaust systems to create
negative pressure for continual airflow through the referenced
structure. The subject blowers were recommended for continuous operation
until vapor-phase petroleum was no longer perceived as a threat to the
impacted residence.
On the afternoon of April 3, 2001, EEI staff met with Mr. Robert Howard
of the DEQ to discuss remedial options for the subject site. EEI
requested interim authorization for the immediate implementation of a
mobile dual-phase extraction and treatment system (DPE) at the site. It
was discussed that aggressive recovery of free, dissolved, and
residual-phase petroleum was necessary to reduce the continual formation
of vapor-phase petroleum. On April 5, 2001, DPE technology was
implemented at the subject site to aggressively address petroleum
contamination on-site. Per DEQ request, the subject system was shutdown
on May 29, 2001 because vapor-phase emissions from the DPE exhaust stack
appeared to be migrating and impacting receptors living in close
proximity to the site. On June 5, 2001, EEI installed an activated
carbon canister to temporarily treat emissions exiting the DPE exhaust
stack. After approximately 24 hours of system operation, air emissions
exiting the subject treatment vessel were measured at approximately 3000
parts per million (ppm), indicating the treatment capacity of the
activated carbon had been significantly reduced. Based on this
information, system operation was halted on June 6, 2001 until a more
effective and permanent air emission; treatment technology could be
implemented to treat emissions emanating from the DPE exhaust stack.
Approximately 1,600 lbs. of petroleum impact were removed with the DPE
system under Interim Authorization. PSCR monitoring activities were also
halted after the implementation of interim authorization and the total
amount of separate-phase removed during this program was approximately
12 gallons.
A CAP Addendum was requested to prescribe a site remedial endpoint for
vapor-phase petroleum and to address off-gas treatment technology for
DPE exhaust stack emissions. It is important to note that two additional
wells were also installed in a narrow grass strip between the site and
impacted residential house during this phase. This involved exposing a
high voltage power line to ascertain whether or not the noted sentinel
wells could be safely installed. A vapor-phase petroleum endpoint was
set for several wells on-site that contained elevated concentrations of
petroleum. The vapor-phase endpoint was prescribed by measuring ambient
vapor concentrations in two wells on-site that had not indicated impact
from any petroleum phase during activities associated with the current
pollution complaint. This determination strategy was utilized to rule
out background soil concentrations not attributable to petroleum impact
(organic matter decay, etc.). The specifications for a thermal/catalytic
oxidation system applicable to DPE emissions treatment were also
investigated and recommended under this phase.
The following activities were completed prior to the re-implementation
of active remediation on-site: 1) permit acquisition to discharge
treated effluent to the City of Roanoke sanitary sewer system; 2)
purchase of the DPE and thermal/catalytic oxidation systems through
formal bidding procedures; 3) directional drilling for the installation
a high-pressure gas line to the site for operation of the oxidation
system; 4) installation of a security system to safeguard remediation
operations and; 5) subsurface trenching and line installations to
designated wells to enable traffic access across the site during active
remediation. DPE and the off-gas treatment unit were implemented on-site
in September 2002 and active remediation operations to address petroleum
impact have generally been on-going to date. The DPE and oxidation
systems are equipped with an automated telemetry system, which enables
remote operation and monitoring of the failsafe engineering alarms. To
date, the DPE system has removed approximately 6.5 tons of subsurface
petroleum impact and separate- and vapor-phase endpoints have been
maintained on-site for the past two calendar months (December 2003 and
January 2004). Additionally, elevated concentrations of vapor-phase
petroleum have not been detected in the impacted residence since
implementation of active remediation under interim authorization. Due to
this progress, the site may enter into a Post-CAP monitoring program
within the next couple of months.
Staff and Resource Involvement:
Mr. Alden and Mr. Swan provided principal oversight and project
management assistance throughout the term of this project. Mr. Lalli has
been responsible for project management since 1999, which included
logistics and strategies for all phases including and occurring after
PSCR monitoring. Mr. Lalli has also been involved with field management
services and scheduling of staff and associated resources. Mr. Tollefson
was responsible for telemetry system installation and programming
activities as well as providing services relating to equipment
repair/maintenance. Mr. Speiden was responsible for the on-site
coordination of the subsurface extraction line installations. Mr. Sexton
and Mr. Lare were responsible for the operation of the drilling
equipment utilized to install the two sentinel wells. Mr. Tollefson and
Mr. Sexton were responsible for all on-site activities relating to the
implementation of the DPE and thermal oxidation systems on-site.
Pertinent equipment owned and operated by EEI during this project
included: 1) ventilation blowers and associated exhaust systems; 2)
Caterpillar 416B backhoe/front-end loader; 3) Freightliner 8CY dump
truck; 4) Oil-sealed DPE and associated treatment system (oil/water
separator, air stripper, and air sparging system); 5) hollow-stem auger
drill rig; and; 6) thermal/catalytic oxidation system. Monitoring well
installation via air rotary was subcontracted to various drilling
companies, however EEI provided field management of all monitoring well
installations. Directional drilling services were also subcontracted
with oversight provided by the EEI project manager.
.
|