Intermet Lower Basin Plant
INTERMET FORMER LOWER BASIN
PLANT, VA PC#1992-0288
Description of Role: Primary Environmental Consultant/Contractor
Key Personnel: Andrew Alden, Christopher M. Swan, III, Chris Lalli,
Jeffrey Fisher,
Project Cost: $457,915.95 to date
Time Period of Project Work: 1997 to present
Client: Intermet Corporation
Client Representative: Mr. Terry Moore
Regulatory Agency: Virginia Department of Environmental Quality (DEQ)
Regional Office(s): West Central (1999 to 2002) and South Central (2002
to present)
Introduction
Environmental Engineering, Inc. (EEI) is presenting this project as an
example of EEI’s ability to assume project management from a previous
consultant and provide CAP development, CAP implementation, and post-CAP
monitoring at a former industrial site. EEI successfully attained free
product endpoints on-site, and anticipates the pending closure of the
pollution complaint case by the DEQ.
Scope of Work:
A fuel oil release from a 20,000-gallon capacity UST was reported to the
Virginia State Water Control Board (now the DEQ) in July 1991. Intermet
Corporation (Intermet) contracted Geotechnical and Environmental
Services to conduct site characterization and submit an SCR to the DEQ.
The SCR (submitted November 1, 1991) documents the installation of 12
monitoring wells. Three of the wells were destroyed during the UST
removal. The SCR indicated elevated TPH levels in the soil and
groundwater.
Virginia Geotechnical Services, P.C. prepared an SCRA (submitted
December 1994) that delineated static water levels, contaminant
concentrations, contaminant and fate transport, and risk/remediation
assessment. The SCRA noted that a free-product level of approximately
0.9 ft was measured in one monitoring well (MW-2).
In January 1995, weekly free-product removal from MW-2 and weekly
monitoring of MW-4, MW-5, MW-9, and MW-12 began. Central Virginia
Laboratories & Consultants, Inc conducted weekly sampling.
Free-Product/Monitoring reports were prepared by Wiley & Wilson.
Due to high fluctuations of the groundwater table, several monitoring
wells were screened below the high water table. As a result, the DEQ
directed Intermet to install additional wells, to be screened
appropriately. Professional Service Industries, Inc. prepared an SCRA#2
(submitted August 1995) that provided additional information on site
assessment, risk assessment, and remediation assessment. The SCRA#2 also
documents the installation of the additional monitoring wells.
EEI was contracted by Intermet to act as the primary environmental
contractor in March of 1999, and was responsible for responding to a DEQ
request for the development of a CAP. The CAP submitted by EEI
concluded, that between 2,142 to 8,414 lbs. of free product existed
on-site. EEI performed a 118-hour DPE pilot study. By the end of the
118-hour pilot study, EEI had recovered an estimated 190 lbs. of
petroleum at an average rate of 1.61 lbs.-per-hour. DPE was the remedial
technology recommended in the CAP based on its high rate of petroleum
recovery and its cost effectiveness. The CAP also recommended that four
new petroleum recovery wells be installed on-site due to the
questionable construction of some of the monitoring wells previously
installed.
Following approval of the CAP by the DEQ, EEI initiated CAP
Implementation by installing four new free product recovery wells, and
consulting with Intermet to obtain an agreement with the local
publicly-owned treatment works (POTW) to discharge DPE treatment system
effluent to the sanitary sewer on-site. The agreement negotiated by EEI
contained strict water quality limits of 10 parts-per-million TPH in the
treatment system effluent. To meet these limits, EEI designed,
fabricated, and installed a 4000-gallon, biologically-enhanced, sparging
system to polish the effluent generated by standard DPE treatment
system.
A mobile DPE system was mobilized by EEI to the site during every month
between October 1999 and October 2002 where free product was detected
on-site in excess of the remedial endpoint. An iron-based scale began to
coat internal components of the DPE systems, which were equipped with
water-sealed LRPs, which caused the DPE system to shut down, and
required extensive maintenance. Fortunately, EEI was able to draw on
its’ fleet of DPE recovery systems to provide systems equipped with
oil-sealed LRPs. The seamless transition from the use of a water-sealed
to the use of an oil-sealed LRP on-site provided a more cost effective
cleanup though a reduction in both maintenance costs and DPE system down
time.
Post-CAP monitoring culminated in the in fourth consecutive quarterly
monitoring report (submitted in November 2003), in which the free
product remedial endpoint had been maintained throughout the quarter.
This was sufficient for EEI to recommend site closure to the DEQ based
upon the successful attainment of remedial endpoints. EEI is awaiting
closure of the pollution complaint case by the DEQ before properly
abandoning all the monitoring and recovery wells on-site.
Staff and Resource Involvement
Mr. Alden has provided engineering oversight and project management
assistance. Mr. Lalli has been responsible for scheduling of personnel
and field equipment to the project since 2001. Mr. Lalli was responsible
for CAP development, including the evaluation of DPE pilot study data.
Mr. Cirillo was responsible for project management during CAP
implementation, which has included oversight of petroleum recovery well
installations; periodic mobilization and operation of a mobile liquid
ring pump DPE system. Mr. Cirillo also provided liaison services between
the client, two subsequent landowners, the local POTW, and the DEQ. Mr.
Jeffrey Fisher was responsible for obtaining permission to discharge
treated petroleum-contaminated water to the City of Lynchburg’s POTW,
and for arranging with the local electric utility for a three-phase
electric power supply on-site. Mr. David Tollefson was responsible for
field installation of three-phase electrical connection and installation
of telemetry capabilities on EEI’s mobile DPE systems. Mr. Cirillo has
handled the drafting of quarterly monitoring reports for the project.
EEI field technicians collected all field data and provided support for
the operation of equipment and machinery.
Equipment owned and operated by EEI that was used on this project
includes mobile liquid ring pump DPE systems, and a 50Kw diesel
generator. Petroleum recovery well installation via was subcontracted to
Bedford Drilling Company, Inc., however EEI provided field of management
all recovery well installations.
|