VIRGINIA STATE POLICE, BRISTOL BARRACKS
VIRGINIA STATE POLICE,
BRISTOL BARRACKS, PC#95-0147
Description of Role: Primary Environmental Consultant/Contractor
Project Team Leader(s): Andrew Alden, Jeffrey A. Fisher, Jr.
Project Cost: $34,887.00
Time Period of Project Work: June 2001 to December 2002
Client: Virginia State Police
Client Representative: Mr. Ronnie Rice
Regulatory Agency: Virginia Department of Environmental Quality (DEQ)
Regional Office(s): South West
Introduction:
Environmental Engineering, Inc. (EEI) is presenting this project as an
example of EEI’s ability to assume project management from a previous
consultant, and provide additional characterization towards the
successful closure of a petroleum complaint generated by a gasoline
underground storage tank (UST) release.
Scope of Work:
This petroleum release was discovered in 1995, when. gasoline vapors
were found to be accumulating in an auditorium at the VDOT regional
complex in Bristol, Virginia. During an investigation, a leaking product
transfer line was found in the gasoline UST system of the neighboring
Virginia State Police Barracks, which are located approximately 100 feet
from the auditorium. This line was repaired; however, when the UST
system was removed from service in early 1996 the tank was found to have
several holes. Free product was eventually found to accumulate in at
least one of the monitoring wells on-site between the release area and
the auditorium. Subsequently, Environmental Options, Inc. of Rocky
Mount, Virginia was hired to provide environmental consulting services,
which included the preparation of an IAM and SCR and all work included
therein.
EEI was contracted by the Virginia State Police to act as the primary
environmental contractor in June of 2001, and was responsible for
further site monitoring and characterization. EEI presented a SCRA in
January 2002 that included the results of site monitoring and a soil-gas
survey, which was conducted to identify possible areas of elevated
residual-phase or separate-phase accumulations. The soil-gas survey
comprised 35 random points between and around the release area and the
VDOT auditorium. The highest concentrations were near the former tank
pit. Site monitoring indicated that several of the monitoring wells
installed by Environmental Options, Inc. had been lost or destroyed due
to localized construction activities. Based on these findings, EEI
recommended a second SCRA, that would further characterize and delineate
the contaminant plumes, as well as operation of a DPE pilot study to
address the periodic accumulation of free phase petroleum product in one
monitoring well.
EEI submitted the second SCRA in June of 2002, which included the
results of the installation of two monitoring wells and the operation of
a one-week pilot study using a mobile DPE system. Placement of the two
monitoring wells was found to successfully define the dissolved-phase
plume, and yielded data sufficient to determine an accurate hydraulic
gradient. Slug tests performed on four monitoring wells provided data
necessary to define hydraulic conductivity.. The DPE pilot study
suggested that recovery via high vacuum remediation was not highly
efficient due to the heavy clay content of the soil and the relatively
minimal amount of apparent contamination. The DPE pilot did however
successfully establish a mass removal rate of 25 lbs per week, which was
useful in the remediation assessment. EEI suggested that a limited CAP
would be appropriate to address the periodic accumulation of free
product in one of the off-site monitoring wells.
The second SCRA prepared by EEI provided the regional DEQ case
coordinator with sufficient data to recommend site closure based on the
successful definition of the dissolved-phase plume and the hydraulic
gradient. EEI properly abandoned all the monitoring wells and submitted
a Site Closure Report in December of 2002.
Staff and Resource
Involvement:
Mr. Alden provided engineering oversight and project management
assistance during EEI’s tenure with this project. Mr. Fisher was
responsible for primary project management and report writing, which
included drafting the two SCRA’s and the Site Closure Report, field
management of the monitoring well installation, and management of the
second DPE pilot study. Equipment owned and operated by EEI that was
used on this project included a DeepRock™ hollow stem auger drilling
rig, a mobile liquid ring pump DPE system, and a 50Kw diesel generator.
No fieldwork was subcontracted to other companies.
|